View Single Post
 
Old 01-24-2012, 12:54 AM
Antares Antares is offline Windows XP Office 2007
Novice
 
Join Date: Aug 2011
Posts: 17
Antares is on a distinguished road
Default Scheduling conflicts in MS Project

Hi

I am having following (attached) notification when want to re-schedule the schedule...
I checked and discovered that I was having "Must finish on" inflexible constraint on a task. And that was making inconsistencies with predecessors/successors imposed on the same task.

Could you advise me how can I see simultaneously all such incorrect "constraints + predecessors/successors with its own constraints" combinations and not to have these notification messages appearing each time for different tasks?

Thank you Best regards
Attached Images
File Type: jpg Question.JPG (22.2 KB, 7 views)
Reply With Quote