Scheduling conflicts in MS Project
Hi
I am having following (attached) notification when want to re-schedule the schedule...
I checked and discovered that I was having "Must finish on" inflexible constraint on a task. And that was making inconsistencies with predecessors/successors imposed on the same task.
Could you advise me how can I see simultaneously all such incorrect "constraints + predecessors/successors with its own constraints" combinations and not to have these notification messages appearing each time for different tasks?
Thank you Best regards
|