01-16-2012, 07:21 AM
|
Expert
|
|
Join Date: Dec 2011
Location: New England
Posts: 1,693
|
|
Hello,
There are a couple of options:
- Create a summary task with 4 subtasks linked Finish to Start -- each 2 hours in duration. Assign 1 bricklayer to each of the 4 subtasks. Summary task duration will be 8 hours - total work will be 8 hours.
- Create a single task and assign the 4 resources. Split your screen (View Ribbon, uncheck the Timeline and check the Detail). Format the Task Form in the lower pane to Schedule. Add 2 hours delay, 4 hours delay, and 6 hours delay to the second, third, and fourth resource.
I hope this helps.
Julie
|