Adding or removing activities after basline
I have a very basic question. When you make your first schedule enter your costs and resources etc you save the baseline and then later you can compare with actuals which I understand. But what if after saving your baseline, you delete or insert activities? Or change the relations between activities? How do you compare your new schedule to baseline and how can you perform earned value analysis in that case, (if you can do it at all)?
|