Quote:
Originally Posted by fraserm
Hi there,
I'm a very new user to Project and am a little confused as to why Project allows you to specify a duration for a milestone.
My, obviously incorrect, understanding was that a milestone was a point in time, a specific 'milestone' that was reached.
Could anyone offer any insight for it?
Many thanks, Fraser.
|
Hi Fraser,
I'll add on here. I've used MS Project since 1992 and have always found the "mark as milestone" to be misleading and confusing. I agree, the usual definition of milestone is a specific point in time. However, not everyone using Project may follow that definition.
Julie