Default Milestone duration without effort

There are occasions where you might want to give Milestone duration but no effort. For example you are using a MS for approval of test results from a customer and desire to mark this with a MS rather than a task. To do this you will need to mark the task as a MS and Fixed Duration and not Effort driven. This will allow duration with no effort/work.