Sorry, but given your description, nothing should have changed. Free slack is related to predecessor/successor information -- are you sure you haven't changed that data?
Do you remove all tracking data? Removing Actual Starts will change scheduled start and may affect link relationships.
If truly all you have done is copied from the Cost field to Cost1 (no copying dates etc) then you should not be seeing any changes in schedule.
Julie
|