Default Project Server 2010 custom calendars

I am using PS 2010 and have a project where we need to assign tasks to some weekends so i have created a custom calendar in the Server Settings/Enterprise Calendars section. In that calendar i have designated three weekends as working days that start from 6 am to 11 pm. But when i try to set a task to any of those weekends Project moves the task to the following Monday. Any thoughts?