Quote:
Originally Posted by JR_12 View Post
Hello All,


Essentially, all I am trying to do is make it so a task ignores the resource's availability and continues to run. It would be ok also if I could assign the specific task a 24 hour schedule so it's never delayed and just runs continually.

Thank you in advance for your help.
Another option, in addition to sullied suggestion to use elapsed duration, is to assign the built-in 24-hours calendar as a task calendar. Double click on the task and on the Advanced tab set the 24-hour hours calendar as the task calendar.

I hope this helps.

Julie