Essentially, all I am trying to do is make it so a task ignores the resource's availability and continues to run. It would be ok also if I could assign the specific task a 24 hour schedule so it's never delayed and just runs continually.
Thank you in advance for your help.
|
Another option, in addition to sullied suggestion to use elapsed duration, is to assign the built-in 24-hours calendar as a task calendar. Double click on the task and on the Advanced tab set the 24-hour hours calendar as the task calendar.
I hope this helps.
Julie