Hi ususer,
I'm afraid the contours don't work that way. If you assigned the resource at 50% and use a contour, Project will not increase the assignment units above the 50% -- therefore it has to increase the duration to spread the same amount of work over lower assignment units.
You can set the task up as fixed duration -- but in that case, the total amount of work will decrease with the max per day at 4 hours.
You can certainly contour the work manually in the task usage or resource usage view.
I hope this helps.
Julie
|