Newbie Working Time Problem
View Single Post
10-10-2011, 04:44 AM
OTPM
Windows 7 32bit
Office 2010 32bit
Expert
Join Date: Apr 2011
Location: West Midlands
Posts: 981
Hi
Make sure you have applied a resource to the task otherwise it
WILL
only show as one day on the Gantt bars.
Hope this helps.
Good luck.
Tony