View Single Post
 
Old 10-05-2011, 01:35 AM
seanpears99 seanpears99 is offline Windows 7 64bit Office 2007
Novice
 
Join Date: Oct 2011
Posts: 12
seanpears99 is on a distinguished road
Default

Hi ABW

Just to show you, if you apply your Actual Start to Complete Through against your summary, you will show green in your marker but you are actually behind schedule.

Also, in some instances, if you have too many nested summaries, MSP employs a weighting to each of the subsequent summaries so it further compounds your problem.

Hope this helps
Sean