Hi Alan
When you export tasks from Project you will always take the Summary Task with your lower level tasks. You cannot just extract low level tasks. However, what you can do in your export map is to include the field called "Outline Level". Then when in Excel you can filter on the lowest level you want to view in Excel using that field as a filter.
Hope this helps.
Good luck.
Tony(OTPM)