Hi
You cannot change the duration of a Summary Task as it is made of up the earliest start and latest finish of the child tasks belonging to it. What you need to do to reduce the overall length of the collection of tasks is to reduce the child task durations.
Hope this helps.
Good luck.
Tony(OTPM)