Hi Doug
Yes this is simple to do without having a date contraint applied (hard date):
Your task Predecessor should have an FS link to your Milestone such as:
45FS-28d
However you need to be careful of how your Milestone date is being derived.
Hope this helps.
Tony(OTPM)
|