View Single Post
 
Old 08-29-2011, 11:59 AM
Doug Sanderson Doug Sanderson is offline Windows 7 64bit Office 2010 64bit
Novice
 
Join Date: Aug 2011
Posts: 2
Doug Sanderson is on a distinguished road
Default Constraining a fixed interval between two tasks

I have a task the must complete four weeks before a milestone. In theory the milestone date might change what is the best way to constrain the earlier task as I don't wish to use a hard date?

In other words I wish to have a constraint that says "task A must finish no later than 4 weeks before Milestone B". Is this even possible in Project?

Thanks!
Reply With Quote