I can't get project to accept fixed start and end dates
Do not ever enter start dates or end dates for a task.

Quote:
I have a task that will take 4 hours to complete, but it will be done over a 1 week timeframe
Change the units.
I suspect you don't understand the relationship between work, duration, and units. I recommend that you get a book or at least do some online studying. This is not PowerPoint; the interface cannot teach all you need to know.

Quote:
If it takes 12 hours to complete, how do I enter that time without messing up the planned hours of 8?
You are supposed to set up the plan in advance of starting working the project. Then save a baseline, then start working the plan. The baseline is a record of what you predicted before the project started so you can compare it to what actually happened.