Master Projects with different Working Days
Hi Guys,
I was wondering whether MS Project 2010 has the ability to include multiple sub projects within a master project all with separate scheduled working weeks/times.
I have set some of the projects up as individual projects (7d working week & 24 hr day ops) and they are fine, however once I import them they are being transferred into the default standard working week of 8 hrs/d & 5 days/week.
Can anyone shed any light on this?
Cheers
Phil
|