Tracking resources in project
Hi all,
Firstly I am new to this forum and relativly new to MS project. I need to create in MS project a way of tracking where each resource is throughout the project.
There are 8 resources (lets just say they are employees) that throughout the project are being shuffled around to different locations. Each employee is equal in terms of skills etc..
I have already been given a MS project document listing all the activities however the resource sheet has been used for locations and now employees.
What I want to do is create a gantt chart with all 8 employees listed on the left with a gantt showing what they are doing and where.
Is this possible without obviously doing it all manually but instead assigning resources (employees) to tasks and then reversing it?
I hope I made myself clear!
Cheers
|