Using Week for project duration, but MSP is adding consecutive days
I am building a project out, and I have weekends as non-project days, and all my office closure and holidays in.
I have been using weeks for task duration, but if I put in 2 weeks, I get 10 consecutive days for dates. It is not skipping the weekend non-work days.
This is true for 4 wks, 6 wks ect.
It also seems to be true if I put in days it does the same thing. 15 days, no weekend breaks.
What am I doing wrong. I thought it that with the task mode to auto, it would auto calculate.
Thank you,
Z
|