Hi

Thanks for your immediate reply.
a) The email issue is solved.
b) By default, the Multiple Resources are shown in Single Column. But I need the Resources to be shown in Different Columns (To differentiate Different Groups of Resources) .
Is it possible in MS Project? Please give your comments.