Default Update Daily progress from excel into MS project.

Dear All,

I am new to MS project and would you kindly help me please with my question:

There is task (actually lots of tasks, but for simplicity i will consider 1 task) that started at some time in the past and gradually was progressing on a daily basis.
So there are daily progress report excel files listing each day how many % was completed.
How can it be loaded automatically into MS Project showing progress of each day / cumulative daily progress to have a curve - visually to see how slow or fast is it progressing and to compare with baseline curve / graph...

Thank you so much ...
P.S. I am almost near zero in MS project..... looking forward to see you replies
Reply With Quote