Hi Dale, first of all thanks a lot for your quick reply! I might have oversimplified my example, my bad: Why I was not happy with FS in the first place might become more clear when I adapt the example as such: task C now requires not only 100% CAESAR but also 20% BRUTUS (task A and B remain 100% CAESAR only). BRUTUS happens to have 2 days availability only after task A ends (ergo Wednesday and Thursday are free, but not Friday when you compare it to the above screenshot).
My hope now was that task C would be shifted to the available resource "gap" Wednesday+Thursday before task B as both are free to be shifted around (as long as it's not earlier than the finishing of task A). Task B would then start on Friday. This was not possible if I had connected them via A -> (FS) -> B -> (FS) -> C. Any idea how to adress this? Thanks, Chris
|