Auto-adjust predecessors
View Single Post
12-05-2023, 07:19 AM
DaleHowardMVP
Windows 10
Office 2021
Advanced Beginner
Join Date: Apr 2023
Posts: 53
No, what you want Microsoft Project to do is not possible. You should set the Actual Duration of the Manufacture task to 10 days and then the software will automatically adjust the schedule of the Receive milestone. Hope this helps.