Open each project individually and then click Project > Project Information. Click the Calendar pick list and select the calendar that will be using for scheduling the tasks in the project. Click the OK button and then save the project. When you create the master project, Microsoft Project will use the correct Project Calendar for each project, which you specified individually. This means that the schedule will be correct for each subproject in the master project. Hope this helps.
|