Different calendars on different schedules
Hey everyone,
is there a possible way in MS Project to build a master schedule with different schedules of subprojects, which are based on different forms of calendars? The difference is that the calendars are from different firms which are located in different areas and states, so they have different holidays, and working rules (4 working days, 5 working days, 6 working days, etc.). If you put the different schedules in one master schedule, the calendar will be synchronized and is the same for every sub project, but I want that every sub project is based on it's original calendar. Is there a way to evade the calendar synchronization in Project?
I want to represent the schedules in a Gantt chart.
|