How to reshuffle tasks not over 1 day but over 1 month
Situation
I have several tasks that need to be completed before a decision meeting can take place.
Such a decision meeting only takes place on the last Thursday of the month.
Problem
If a task is delivered (to) late, the decision meeting can therefore only be scheduled a month later.
For example, there are 4 tasks and there is a precondition for scheduling a decision meeting (T5) that it can only be scheduled on the last Thursday of the month.
Question
Is it possible to automatically postpone the T5 not 1 day but, for example, 1 month in the event of a late delivery of a task?
By default, Project calculates next day to start follow-up task.
So now we have a precondition for rescheduling that task.
You understand, I can check and adjust this manually, but can that be included in MS Project?
(Within municipal institutions, this is too common to continuously correct manually)
|