Hi Everyone!
I'm trying to use MSProject to track different projects in the company I'm working for.
I'll be using the Duration with a calendar with working days in order to: assign public holidays, allocate resources, and see if I'm over capacity and need to expand (bringing more people to the project). I still need to learn how to create this.
At the same time, I need to be able to see the elapsed time. I'm doing this using a number column with custom fields driven by a formula that calculates the difference between Start and Finish. This works perfectly for tasks, but it shows 0 for Summary tasks (picture below), can this be solved? Having the time for the Summary Tasks will help a lot in knowing how much each phase will take.
(EDIT: Image URL as Image not displaying
Capture hosted at ImgBB — ImgBB )
Thanks!!!