Having problems with Duration calculations.
I have Type set to Fixed Work, as I want Duration to adjust based on the Resources I add to the ask, leaving the Work static. I have one resource setup to work 8hrs/day, and a second resource to work 4hrs/day. I set the Work to 5d for a task. However, when I assign Resource 1 and Resource 2 to the task, each @ 75%, the Duration is set for 3.33d. I would assume it should be set for 4.44d based on 40hrs (5d) / 9hrs (6hr + 3hr). Where am I going wrong with my calculations?
|