Default

Hi Tony,

I am trying to create a view that will display Resource assignment and any task level variance (Ahead / Slippage # of days). This will help in discussing weekly review with the resource managers to prioritize workload.

I tried following steps:

a. Created 2 custom Resource level Date fields, with field value formulas (1) BaselineStart & (2) Start respectively.

b. Created a custom Resource level Number field, with field value formula (difference of above created custom date fields).

I inserted the custom number field in Resource Usage view and unfortunately, getting 0 value. I have attached sample project with this changes.

Pls advise,

Thanks in avance,