Hi Tony,
I am trying to create a view that will display Resource assignment and any task level variance (Ahead / Slippage # of days). This will help in discussing weekly review with the resource managers to prioritize workload.
I tried following steps:
a. Created 2 custom Resource level Date fields, with field value formulas (1) BaselineStart & (2) Start respectively.
b. Created a custom Resource level Number field, with field value formula (difference of above created custom date fields).
I inserted the custom number field in Resource Usage view and unfortunately, getting 0 value. I have attached sample project with this changes.
Pls advise,
Thanks in avance,
|