Thread: [Solved] Project start date
View Single Post
 
Old 05-17-2011, 07:12 AM
OTPM OTPM is offline Windows 7 32bit Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Steve

All you need to do is first of all check that your schedule runs from the Project Start Date. To do this select Project followed by Project Information from the drop down list and you will see a field called Schedule From. Make sure that field is set to Project Start Date.
Once you have done that all you need to do is change the project start date in the same dialog box. This will move your project as you requested.
Tony
Reply With Quote