View Single Post
 
Old 05-02-2023, 07:17 AM
ICNARC261 ICNARC261 is offline Windows 11 Office 2021
Novice
 
Join Date: May 2023
Posts: 1
ICNARC261 is on a distinguished road
Question Actual number of days working on the task VS period of time to complete the task

Hi All,

You may find my question stupid, but after a long hassle, I decided to ask for help.

Given: Say I input a new summary task for the project and say this summary task has 5 tasks. The time period for each task is 1 week (5 days) and the time gap between tasks is 3 weeks (15 days). I set the project time to be calculated in days. After all that, my summary task shows that the total amount of working time is 100 days (working + gap), instead of 25 days of actual work.

Pop-quiz: how can I set the summary task to show the actual amount of working time instead of the total time including gaps?

Sorry if it all sounds confusing, I tried to be as specific as I could.
Thanks to everyone in advance!

P.S. I use MP 365
Reply With Quote