Default Task only on 2nd Thursday

I have a task (Meeting B) that can only occur on the 2nd Thursday of each month. Additionally, it can only take place after Meeting A and Meeting A MUST be held at least 45 days before Meeting B.

I can't figure out how to get Project to constrain Meeting B to only the 2nd Thursday of each Month and 45 days after Meeting A. Thoughts?