View Single Post
 
Old 12-04-2022, 01:48 AM
Guloluseus Guloluseus is offline Windows 7 64bit Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

If your milestone date is the start or finish of a task, you could format the bar to show the date on the bar.
Apart from that, without resorting to VB (which MIGHT do it), then no. Its not a simple ask, in reality, as MSP shows a task per line, and a milestone is a separate task, so you would be trying to put two items into one line.
Reply With Quote