Default Creating a custom field for tables in reports, showing the hours/week of a task

Hi everyone, I'm working on some rapports and I would like to have a row that indicates the hour per week.

For example, The duration of a task might be 2 weeks, and the work might be 40 hours,
I would like the custom field to calculate a simple divying up of the work effort, per week, in this case it would be 20 hrs per week. If it was 5 weeks and 50 hours, it would show as 10 hours a week. From there it should be easy to get it into a table row, showing it per task as a list.
It's quite likely this must be possible using the custom field programming right? I've been having a look at it but I can't figure it out myself.
Any help would be tremendously appreciated.