Issue Importing Column from Excel
I am a new user to Project but have decent knowledge and understanding. I was previously able to import a file from Excel without issue but now I cannot map Task Name. I select New Map/New Project and select Task as the type of data to import and include headers. When i select the source worksheet, all the fields map except Task Name. This field is also not in the pick list. It was previously, so I must have done something unwittingly. Not sure what or how to correct.
If I select Resource as the type of data, nothing will map and the field names are not available to pick.
If I select Assignment as the type of data, the Task Name will map but nothing else.