View Single Post
 
Old 06-21-2022, 02:18 PM
JHalter JHalter is offline Windows 10 Office 2019
Advanced Beginner
 
Join Date: Nov 2021
Posts: 50
JHalter is on a distinguished road
Default Resources and Fixed Work

I have a task with 3 resources assign like so..
Engineering. baseline work .3h
Test baseline work 1h
Assembly baseline work 5h

The actual work was only performed by assembly at 3h and now the task is 100% complete. How do I get the task to show 100% complete without filling in actual work for engineering and test?
Reply With Quote