Hi,

I've created s sample Gantt chart as attached. It has a "Summary Task", "subtask", and 2 individual tasks.

After I've switched it to network diagram view, there are arrows between individual tasks only. There are no arrows between "Summary Task", "subtask", and the first individual task. Is it possible to have arrows to link these? If so, could you show me the steps/