Make your
Lorry Hire Task a
Hammock.
To create a hammock,
copy the
start date of the first Task that uses the equipment and use
Paste Special >> Paste Link, to
paste in the
start date field of the
Lorry Hire Task.
Similarly,
copy the
finish date of the last Task that uses the equipment and use
Paste Special >> Paste Link, to
paste in the
finish date field of the
Lorry Hire Task.
Your Lorry Hire Task should now be
dynamically linked to equipment use and a change in equipment use Tasks duration will also change Lorry Hire duration. You can confirm Lorry Hire is dynamically linked as there should be a
small black triangle at the bottom right corner of the Start & Finish dates.