Summary shown as critcial path
Hi,
Iīve got a hugh plan setup and it worked very well, also highlighting the critical path worked from beginning to the last milestone.
Now, when I want to highlight the critcal path and filter the processes it shows me about 10 processes as it should and after that 10 it shows only the summary processes (Phases of the project) as critical, not the sub processes that really drive the critical path.
I already checked for limitations but couldnīt find some.
Thank you very much for your help!
Jen
|