Hey
Probably a question asked may times... Im not looking for this by task, just a single Actual vs scheduled % value that i can deliver to my management team as this is the main question to me...
so, i need to get the following values
1. the percentage through the scheduled project. If it was a 100 day project and im current 50 days in, this value would be 50%
2. the percentage of actual completed work. If it was a 100 day project, im at 50 days but have completed 65 days work, the value would (50%) 65%
3. the percentage ahead of actual completed work. If it was a 100 day project, im 65%, 15% over the schedule, the value would be 15% ahead
I can do a report, i'd like to know if
- Project can already provide these values
- What fields would i need to calculate to do this myself
Thanks