View Single Post
 
Old 03-17-2022, 12:58 PM
NachoShaw NachoShaw is offline Windows 10 Office 2021
Novice
 
Join Date: Mar 2022
Posts: 1
NachoShaw is on a distinguished road
Default Project Progress - Actual vs Estimated

Hey

Probably a question asked may times... Im not looking for this by task, just a single Actual vs scheduled % value that i can deliver to my management team as this is the main question to me...

so, i need to get the following values

1. the percentage through the scheduled project. If it was a 100 day project and im current 50 days in, this value would be 50%

2. the percentage of actual completed work. If it was a 100 day project, im at 50 days but have completed 65 days work, the value would (50%) 65%

3. the percentage ahead of actual completed work. If it was a 100 day project, im 65%, 15% over the schedule, the value would be 15% ahead

I can do a report, i'd like to know if
  • Project can already provide these values
  • What fields would i need to calculate to do this myself



Thanks
Reply With Quote