View Single Post
 
Old 01-20-2022, 04:06 AM
joday48 joday48 is offline Windows 7 64bit Office 2010 32bit
Novice
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Project Summary Task formula to show milestone progress

I have a client who is struggling to understand why milestones progress is not reflected in the project summary task. I have a schedule structured as follows:

-Build milestones
-Design milestones
-Production tasks (fixed work, all resourced).

Is there a formula (or some other way) that I can use to reflect the progress of the milestones at summary task level?

I have attached a couple of snap shots of my schedule if that is helpful.

Thank you
Attached Images
File Type: png Summary.PNG (275.9 KB, 9 views)
File Type: png Production.PNG (267.8 KB, 9 views)
Reply With Quote