Milestone reports
Hi all
I have MSP 2019.
I have various plans I will be looking after.
I want to run a milestone report for certain stages of a project.
Currently the milestone report shows all milestones, yet I only want to show milestones for certain sections (parents).
For example
Portfolio 1
Project A
Milestone 1
Milestone 2
Project B
Milestone 3
Milestone 4
So, can I run a report showing only milestones 1 and 2, not 1,2,3 and 4.
Thank you in advance!
|