Default Highlight late tasks incorrectly highlighting

Hi All,

I am trying to use the highlight feature within MS project but when I select "highlight late tasks" it highlights tasks that have an end date way into the future such as March 2022.

I have googled this issue and haven't really been able to figure out a solution to this issue. The project overview report also reports that those same tasks are late while also showing end dates that are months in the future.

Does anyone know what I could be doing wrong here?

Thanks!