Default Different % complete in Project Center & View a Project

First you check the field names, both should be either % Complete or % Work Complete. If you are looking % Complete in PWA and % Work Complete in Project Professional, the values will be different.


If that is not the case then, you have to do the following steps to align the % complete/% Work complete in Project Professional and PWA.

1. Open the project plan using project professional
2. Select |Collaborate | Publish | Republish Assignments
3. Check (tick) Overwrite actual work entered by resources
4. Click OK button

This action will push the values from Project Professional to PWA, including individual resource timesheets.