Thread
:
Fixed Work Unit Calculation
View Single Post
11-05-2021, 09:49 AM
JHalter
Windows 10
Office 2019
Advanced Beginner
Join Date: Nov 2021
Posts: 46
Fixed Work Unit Calculation
I have all tasks set to fixed work, I want the units to be calculated. I currently have 10 day duration and 4 hours of work, but the units aren't calculating. How do I fix this?