Dear MS Project professionals,
In would like to do an analysis on my plan.
For this analysis I would like to level only 2 of my 10 resources.
Is it possible to process that kind of resource leveling?
If yes: How?
The reason for this approach is, that the other 8 resources can easily be levelled manually and I want to level them afterwards.
Thank you very much in advance.