Default Custom Calendar

Hi buddies, I hope all of you are doing well.

I am using Microsoft Project Online MSO (16.0.14026.20294) 64 bits, I created and set up a custom calendar with its working time and work exceptions.

Then I selected Project from the main menu and clicked the button Project Information for me to assign my custom calendar to my Project tasks.

But it came to happen that later, I double-clicked a task and selected the advanced Tab to figure out that in the field Calendar says None when I expected to see my custom calendar.

I wonder if I followed the right procedure to assign a custom calendar to all tasks of my Project Schedule, or my Microsoft Project is not behaving as expected.

I hope you can help me to understand what's going on.

Thank you all.