Summary task does not summarize % complete
Hi guys,
recently I added a custom field in my Project Schedule to show % complete with decimals, thanks to Jerome´s reply to a previous thread I posted in the forum.
Now I am using the same custom field to show %complete with decimals, but I notice that when I have a summary task that contains only milestones (activities with a duration of zero days), when I update the % complete to one or some of the milestones within that summary task, the summary task remains showing 0%, unless I give 100% compete to all of its subtasks.
Is there any way for a Summary task that contains only milestones to summarize the total % complete when some of its milestones reach 100%?
|