Quote:
Originally Posted by ProjectPlanner
Replace the semi-colons with a comma, so that the formula for finish is "Week " & CStr(1+datediff("w","1/1/20" & mid(Year([Finish]),3,2);[Finish]))
explanation.
mid(Year([Finish]),3,2) = extracts 2 characters from the year of the finish date starting at the 3rd character. E.g. for "04-Jun-21", year is 2021 and the formula extracts 21.
The 21 from above is then joined to "1/1/20" to form "1/1/2021".
|
Thank you.
Why only "," on the FINISH formula? Should be on START and DEADLINE too?
The same logic of "mid(Year([Finish]),3,2);[Finish])" is same for START and DEADLINE?
I guess you don't know how to accommodate to make the weeks correct? Year starting with first four day week....etc.
Thanks again