View Single Post
 
Old 05-31-2021, 02:45 AM
fouad.khoury fouad.khoury is offline Windows 10 Office 2019
Novice
 
Join Date: May 2021
Posts: 1
fouad.khoury is on a distinguished road
Default Custom formula for % completed

Hello,


i noticed that Microsoft Project is not reflecting the accurate percentages of work completions in the following case: (for ex it is showing let's say 40 % progress where the real is should be 30%)

- if a task has duration of 4 days and the task has delayed to 14 days due to delay from customer or for any reason: in this case % completed is still same but after let's say 4 + 14 +5 days it get completed: the total duration now is high and having impact on overall percentage of project due to increase on number of days.


the question is:
how to accommodate this? can we add a custom formula dealing with custom fields?

Kindly advise
Regards,
Fouad
Reply With Quote